Tim nailed it right on the head with his above writeup. This will be our teams first race/event so we are in total thrash mode the next few weeks. Full weekend of wrenching for most of the guys on my team this weekend. I'm actually heading to the garage in about 2 hours to assist. Again, I don't want to reveal too many details on the car/project yet, but we have the cage 95% in, car "painted", engine running (a few leaks to contend with), exhaust run, seat installed, brakes, wheels tires, brake ducts setup, fuel system plumbed and tested, cooling system setup (need new water pump), etc. A lot of the next stuff these two weeks involves wiring EVERYTHING, tuning the engine better, testing that the transmission even works, sorting out kinks, grabbing a full trailer and loading up all the gear/tools/ car, etc totally a fun project, but not as much with the deadline only 2 weeks away.